Pay Back Analysis
STEAM LEAKS
At Sun Co.'s Toledo, Ohio refinery, the Ultraprobe identified 188
malfunctioning steam traps. Savings from replacing these traps have
been in the range of $56,000 per year based on reducing 450 p.s.i.
steam consumption by about 1,000 lb./hr.
Chevron USA, Perth Amboy NJ has six to eight thousand steam traps
throughout the plant. The plant generates close to 500,000 lb./hr.
of steam. A steam trap audit with the UE SYSTEMS' Ultraprobe
revealed the trap failure rate was up to 28%. The refinery has
increased its steam trap reliability by 15% within two years after
the Ultraprobe was put into use. The reduction in steam losses is
savings at least $50,000 a month.
Indiana University-Perdue University campus at Indianapolis has
three to four thousand steam traps. Technicians using the
Ultraprobe to monitor steam traps and bypass valves estimate they
are saving $300,000 per year.
AIR LEAKS
In a 75 p.s.i. system with a production cost of $0.14/m cu. ft., a
number of leaks totaling 1/4" will cost $5,734.15 in a year. Double
that to 1/2" and the cost of wasted air will be $22,940.25.
In a 100 p.s.i. system, based on nozzle coefficient of .65, and a
production cost of $0.10 per thousand cubic feet, a number of leaks
totaling 1/8" will result in the loss of 740,210 cubic feet of air
per month, at a cost of $74.01 per month. Triple that to 3/8" and
the waste will be 6,671,090 cu. ft. per month and $667.19.
BEARINGS
A bearing on one of our client's two 500 H.P. motors froze up and
did $2,500 damage. Using the stethoscope (contact) module, they
picked up a bad bearing noise on the second motor . . . resulting
in immediate repair and avoiding a complete shutdown in one area of
the plant.
Related to another client, on a Saturday, when the shop was shut
down, maintenance personnel used a regular stethoscope and picked
up a bearing noise with the machine running at low speed. The
housing they listened to contained two bearings at a cost of $1,500
each. Their stethoscope could not determine which bearing was going
bad. With the plant back in operation on Monday, and all other
machinery running the Ultraprobe was brought in to check the
machine in question, while running at top speed. The Ultraprobe
identified the front bearing as being the culprit while the back
bearing was okay. They immediately replaced only the front bearing
at a cost of $1,500, and were back into production much sooner than
would have been the case had they replaced both bearings.
And again another client, one of the largest construction
companies in the Southwest USA uses an Ultraprobe to check the
hydraulic systems on earth moving equipment, tower cranes, etc. In
a recent case, ten minutes of PM prevented the destruction of two
pumps worth $2,000 each, two or three days down time in the midst
of a project with operators and other worker standing idly by; the
cost of eight hours maintenance time (at overtime rates); air
freight charges to fly in new pumps; and even the possibility of a
penalty for the delay in completing the project.